Pre Installation

This section describes the recommended location and environment required for best performance of the Onyx FHM and the materials and tools needed to install the Onyx FHM.

Installation Location

The Onyx FHM is designed to be installed in either a 19-inch standard rack or chassis that conforms to EIA-310 dimensions, or to be mounted flush to a wall.

When front mounted in a 19-inch Rack or Chassis, the rack or chassis must have a front-to-back clearance (depth) of no less than 10.9 inches (277mm).

The Onyx FHM is air cooled by its integrated fans and relies on intake air that has a temperature of -40°C to 65°C. Ideally, the rack/chassis shall reside in an indoor climate-controlled environment. Additionally, if a 19” server chassis is utilized, adequate airflow through the chassis and clearance of at least 6 inches (153mm) from the front doors of the chassis must be ensured.

Do not install the Onyx FHM where the relative humidity of the surrounding air can exceed 95% or where it will be exposed to falling or dripping water or other liquid contaminates.

To best ensure long-term performance of the Onyx FHM, install the device in a location with minimal dust in the environment, or where dust mitigation (air filtering) is present.

Common Installation Tools

Adjustable Torque Driver

#2 Phillips Driver Bit

Percussion Drill or

4mm Concrete Drill Bit 2mm / 4mm HSS Drill Bit 3/8-Inch HSS Drill Bit

Level bar

10mm Wrench

#2 Phillips-Head Screwdriver

Hydraulic Crimping Tool

Wire Stripper capable of 6 AWG and 14 AWG wire

Other Required Items (Installer to Provide)

1

A length of 6-AWG Green/Yellow to terminate to the Onyx FHM Grounding Lug.

Terminated end shall have 0.5 +/- 0.02 inch (12.7 +/- 0.5 mm) of insulation removed.

Stripped 6-AWG Wire Details